Selection conditions
Ask how the plant handles a module fault. A drawer build lets the engineer swap the unit without a line stop, which changes maintenance planning. Confirm that N+X redundancy is specified, then check the space needed to slide a drawer out.
Corresponding parameters
Regulation holds at ≤1% for voltage and current across the 0–1000kVA range. Power factor is 0.94. Pair the drawer enclosure with the synchronous platform when current sharing within 1% and N+X redundancy are required.
| Parameter | Value |
|---|---|
| Power range | 0–1000kVA |
| Voltage / current regulation | ≤1% |
| Power factor | 0.94 |
| Module service | hot-swappable drawer |
| Redundancy option | N+X with the synchronous platform |
Process fit
Continuous plating lines at 500–8000A and electrolysis lines at 0–50000A value the drawer format because a fault no longer sets the maintenance window. Parallel count still follows total project power. Site expansion steps belong in the technical agreement.
Lead time and warranty
Standard and custom drawers ship in 15–20 days with a one-year warranty. Confirm the slide-out clearance on site; that is an installation condition rather than a published product figure.